SITEMAP| CONTACT| CHINESE| ENGLISH Welcome to Guangdong LongHong Electrical Equipment Co.,Ltd

Service Hotline��135-4996-2688

Guangdong LongHong Electrical Equipment Co.,Ltd

Contact us

Address:广东省佛山市顺德区陈村镇岗北工业区中路2号-1(导航:隆宏机电)

Sales Hotline:0757-23302558 400-617-3066 

Fax:0757-23305005

Mobile:13549962688

Email:wd@wdfdj.com 

After-Sale Service Hotline:400-669-1663

Home >NEWS>Group news

Foshan generators - diesel generators use common sense and maintenance

Date:2016-09-24 09:51:14

First, the unit before starting the preparation
1, check the oil level, coolant level, fuel volume in the provisions of the scale line in the specified range.
2, check the diesel engine oil, lubrication, cooling systems, such as the various pipes and joints without oil leakage, water leakage.
3, check whether the electrical circuit breakage and other hidden dangers, ground and electrical lines are loose, the unit and the foundation of the connection is strong.
4, if the ambient temperature is below zero, in accordance with the instructions on the proportion of the radiator to add a certain percentage of antifreeze.
5, the first diesel generator set to start or shut down after a long time to start again, the fuel system must be exhausted air.
6, the generator into the line switch cabinet trolley to work position, check the energy storage switch is in place.

Second, the unit starts
1, close the control box of insurance, press the start button, press the button 3 ~ 5s, if the start is not successful, should wait about 20s to start again. If the start is not successful many times, should stop the start operation, remove the battery voltage or oil and other fault factors, start again.
2, start should observe the oil pressure, if the oil pressure is not displayed or very low, should immediately stop inspection.

Third, the unit operation
1, after the start of the unit, check the parameters of the control box module: oil pressure, water temperature, voltage, frequency and so on within the specified range, and every 1 hour into the record book.
2, under normal circumstances, the unit starts directly after the rated speed; idling requirements of the unit, the idle time is generally 3 ~ 5min, idle time is not easy too long, or may burn generator-related components.
3, check the unit oil, water and electrical leakage.
4, check the connection of the unit tightening to see whether the loose and severe vibration.
5, observe the various protection and monitoring unit is normal.
6, check the generator temperature is within the specified range.
7, when the speed reaches the rated speed, no-load operation of the parameters of stability, the closing power supply.
8, check the control panel to confirm whether the parameters within the allowable range, once again check the unit's vibration, with or without three leaks and other failures.
9, the unit is running overload operation is strictly prohibited.
4, unit parallel operation
1, will set up a first machine for the host, a later set up as a slave machine.
2, to be the first stable operation of the generating units, and then the second parallel operation.
3, two machines running side by side, we should pay attention to observe the size of the reverse power, under normal circumstances between 1 to 10KW, if beyond this range for processing with the manufacturer.
5, the normal shutdown
Before the shutdown must be sub-gate, generally required to run after unloading 3 ~ 5min downtime.
6, emergency shutdown
1, abnormal operation of the generator unit, you must immediately stop, and timely reporting of mine scheduling.
2, emergency stop, press the emergency stop button or fuel pump stop control handle quickly pushed to the parking position.

Diesel generator room management system
First, the electrician must operate according to the rules, the correct use of generators, generators usually do a good job in the maintenance work, each power to do a good job of recording.
Second, the various parts of the generator, coolant, fuel, battery often check to maintain good condition, to ensure that the unit ready to start generating electricity.
Third, in case of high-voltage power line power failure, half an hour should ensure that power generation, power transmission.
Fourth, the generator unit must be guarded by hand, check the control box on the display of the parameters are normal, identify problems and timely reporting to the leadership.
5, to keep the generator clean and tidy, near the generator may not be stacked debris, special tools to be placed in the toolbox.
6, to ensure that the diesel engine box has sufficient diesel, after each power generation to fill the diesel in time to prepare for the next power generation.
7, unrelated personnel are not allowed to enter the computer room, after the approval of the leadership before entering.
8, prohibit the use of fire in the engine room to prevent accidents.
Responsibility System for Diesel Generator Operators
First, the operator must master the basic structure of the generator, and can handle a simple fault.
Second, the operator must be able to operate in accordance with the generator rules, the correct operation of the use of generators.
Third, we must always do a good job generator maintenance work, all parts of the generator, coolant, fuel, battery often check to maintain a good state, to ensure that the unit can start generating at any time.
Fourth, the generator is running, the operator must adhere to the post, shall not leave their duties.
Fifth, the operator should run every time the operation of the generator and the operation of the problems seriously fill in the record book, and timely maintenance workers for processing.
6, the engine room equipped with fire equipment must be proficient in use, if the fire can be promptly put out.
7, during the generator operation, such as loitering may not enter the room.
8, the generator room should be kept out of the window, the generator may not be stacked near the debris, special tools to be placed in the toolbox.

Foshan Generator, Guangzhou Generator ---- Foshan Longhong Electromechanical Equipment Co., Ltd

Diesel generator room management system
First, the electrician must operate according to the rules, the correct use of generators, generators usually do a good job in the maintenance work, each power to do a good job of recording.
Second, the various parts of the generator, coolant, fuel, battery often check to maintain good condition, to ensure that the unit ready to start generating electricity.
Third, in case of high-voltage power line power failure, half an hour should ensure that power generation, power transmission.
Fourth, the generator unit must be guarded by hand, check the control box on the display of the parameters are normal, identify problems and timely reporting to the leadership.
5, to keep the generator clean and tidy, near the generator may not be stacked debris, special tools to be placed in the toolbox.
6, to ensure that the diesel engine box has sufficient diesel, after each power generation to fill the diesel in time to prepare for the next power generation.
7, unrelated personnel are not allowed to enter the computer room, after the approval of the leadership before entering.
8, prohibit the use of fire in the engine room to prevent accidents.
Responsibility System for Diesel Generator Operators
First, the operator must master the basic structure of the generator, and can handle a simple fault.
Second, the operator must be able to operate in accordance with the generator rules, the correct operation of the use of generators.
Third, we must always do a good job generator maintenance work, all parts of the generator, coolant, fuel, battery often check to maintain a good state, to ensure that the unit can start generating at any time.
Fourth, the generator is running, the operator must adhere to the post, shall not leave their duties.
Fifth, the operator should run every time the operation of the generator and the operation of the problems seriously fill in the record book, and timely maintenance workers for processing.
6, the engine room equipped with fire equipment must be proficient in use, if the fire can be promptly put out.
7, during the generator operation, such as loitering may not enter the room.
8, the generator room should be kept out of the window, the generator may not be stacked near the debris, special tools to be placed in the toolbox.

Foshan Generator, Guangzhou Generator ---- Foshan Longhong Electromechanical Equipment Co., Ltd